A bank usually does not release a mortgage on a flat from a developer all at once. How the drawing stages follow the payment schedule, what you pay during construction and how the security works.

In short

  • A mortgage can be drawn at once or in stages under the payment schedule of the future purchase agreement; the money goes to the developer.
  • While the loan is being drawn you usually pay only interest on the amount drawn; principal repayments start once it is fully drawn.
  • The drawing period is usually 24 months; for developer projects some banks allow up to 36 months.
  • The lien on the flat arises by entry in the land register; until the unit exists in the register, the bank arranges the security differently and sets its own conditions.

How is a mortgage drawn on a flat that does not exist yet?

A bank draws a mortgage on a flat from a developer either at once or in stages, depending on the purpose of the loan; for a flat under construction that means in stages under the payment schedule in the future purchase agreement (SoSBK). The mortgage money is paid to the developer under a pre-agreed timetable and the terms of the contract.

You first pay the developer your share from your own funds; the bank then pays the rest of the purchase price. How much of your own money you need is set by the ČNB LTV limit: at most 80% of the value of the mortgaged property, or 90% for applicants under 36 buying their own home.

Before the contract is signed the bank thoroughly assesses your creditworthiness (Consumer Credit Act section 86), and it may not change or withdraw its proposed mortgage terms for 14 days (section 111).

What happens at each stage?

A typical course for a flat under construction. The amounts and dates of payments are always in the payment schedule of the specific contract.

What happens at each stage?
StageYou payWhat the bank does
Reservationa reservation feeNothing; you are only applying for the mortgage.
Future purchase agreementthe first deposit from own fundsAssesses your income, has the flat valued and signs the loan agreement.
Constructiondeposits per the schedule, interest on the amount drawnReleases tranches to the developer under the timetable and the terms of the contract.
Occupancy permit and handoverthe balance of the purchase priceDraws the rest of the loan; at some banks only after the purchase contract is signed.
Purchase contract and land registerthe administrative fee for the entryThe lien on the flat arises by entry in the land register (Civil Code section 1316).
Fully drawnfull repayments (principal + interest)Repayment starts under the loan agreement.
Reservationa reservation fee
Nothing; you are only applying for the mortgage.
Future purchase agreementthe first deposit from own funds
Assesses your income, has the flat valued and signs the loan agreement.
Constructiondeposits per the schedule, interest on the amount drawn
Releases tranches to the developer under the timetable and the terms of the contract.
Occupancy permit and handoverthe balance of the purchase price
Draws the rest of the loan; at some banks only after the purchase contract is signed.
Purchase contract and land registerthe administrative fee for the entry
The lien on the flat arises by entry in the land register (Civil Code section 1316).
Fully drawnfull repayments (principal + interest)
Repayment starts under the loan agreement.

What do you pay while drawing, and by when must the loan be drawn?

While the loan is being drawn you pay only interest on the amount drawn; principal repayment starts once drawing ends. Česká spořitelna and Komerční banka both state this, and other banks have the same in their terms: mBank, for example, charges only interest until the loan is fully drawn, but for at most 24 months from the first drawing, after which full repayments start.

The drawing period is usually 24 months. Komerční banka allows up to 36 months for a mortgage on a developer project, against the standard 24. Compare the period with the completion date in the future purchase agreement; construction delays are common with new builds.

If the bank also finances the developer’s project itself, it knows the building and the flat and often already has the valuation and the construction documents, so you do not have to supply documents on the property (Komerční banka). Ask the bank or the developer directly which projects the bank finances.

What secures the loan when the flat does not exist yet?

A unit comes into existence by the entry of the owner’s declaration (prohlášení vlastníka) in the land register (Civil Code section 1164), and a lien on a thing recorded in a public register arises by entry in that register (section 1316). The Land Register Act does not record units under construction; until the owner’s declaration is entered, the flat you are buying therefore does not exist in the land register as security.

Banks handle this under their own rules: a lien on another property, a lien on the building under construction, or, for projects they finance, a lien that the developer signs on the unfinished building for you (Komerční banka: “you are guaranteed that the developer will sign the lien”). mBank states that the flat being bought, a house or a property under construction can serve as security and that it draws already on the basis of the application to register the lien.

Find out which security the bank accepts for the specific project and when it releases the first tranche before you pay the reservation fee.

Which value does the bank calculate LTV from?

The security of a mortgage is valued at the usual price or market value, and the valuation must be impartial and objective (Consumer Credit Act section 113(3)). For a loan for construction or renovation it is the value of the property after completion (Decree No. 399/2021 Coll. section 2); for a flat under construction banks therefore work with the future value.

The LTV limit is calculated from this value, not from the purchase price. If the valuation comes out lower, you get a smaller loan and pay the difference from your own funds.

What to ask the bank before you sign

0 of 6 checked

What a new-build flat costs today

Median prices of flats on sale, data as of 25 Nov 2026.

CZK/m², median for Czechia
174,088
CZK/m², median for Prague
187,072
a 60 m² flat at the Czech median
10.4M CZK
20% own funds of that price
2.1M CZK
€/m², median for Czechia
7,126
€/m², median for Prague
7,657
a 60 m² flat at the Czech median
€427,600
20% own funds of that price
€85,500

Illustration: a 60 m² flat at the Czech median price per m². The loan follows the bank’s valuation, not the purchase price.

FAQ

Usually not. While the loan is being drawn you pay only interest on the amount drawn; full repayments start once it is fully drawn. Some banks limit the interest-only period, though: mBank, for example, to at most 24 months from the first drawing.

What next

Sources: Komerční banka: mortgage for a new build or developer project; Komerční banka: mortgage for a new build from a developer; Česká spořitelna: when and how can I draw a mortgage; mBank: terms for mortgage loans (article 7.1.3), effective from 13 November 2025; mBank: home mortgage; Consumer Credit Act, No. 257/2016 Coll. (sections 86, 111, 113 and 117); Decree No. 399/2021 Coll. on credit indicators (section 2); Civil Code, Act No. 89/2012 Coll. (sections 1164 and 1316); Land Register Act, No. 256/2013 Coll. (section 3); ČNB: LTV upper limit.

The guides are for information only and do not replace legal, tax or financial advice. Always check the terms of a purchase in the contract and with your bank.