Guides
Handover6 min read

Handover of a flat from a developer

Occupancy permit (kolaudace), handover protocol, rights for defects, floor area and the energy performance certificate: what to check before you take the keys.

In short

  • A building that requires a permit may be used only on the basis of an occupancy decision (Building Act section 230).
  • Report obvious defects without undue delay; a hidden defect of a building can be reported within five years of acquisition (Civil Code sections 2112 and 2129).
  • The floor area of a flat is measured under Government Regulation No. 366/2013 Coll. including internal walls; balconies, terraces and cellars are not rooms of the flat.
  • The seller must show you the energy performance certificate (PENB) before the contract is concluded and hand it over at the latest when the purchase contract is signed (Act No. 406/2000 Coll. section 7a).

When can the developer hand over the flat?

A finished building may be used only on the basis of an occupancy decision (kolaudační rozhodnutí): a building that requires a permit may be used only on that basis and only for the purpose it defines (Building Act section 230(1)). Developers’ contracts therefore usually tie the handover to the occupancy permit (kolaudace).

If the conditions are met, the building authority issues the occupancy decision within 15 days of the final inspection or, if it holds none, within 15 days of the application (section 235). Before completion the authority may permit early use of the building for at most one year (section 236).

The handover is followed by the purchase contract and the entry in the land register; you become the owner by the entry, effective from the day the application reached the cadastral office. When you pay the balance of the price is set by the payment schedule in the future purchase agreement.

What to check at the handover and write in the protocol?

0 of 8 checked

What rights do you have for defects of the flat?

Under the Civil Code. What matters is whether the defect is obvious or hidden, and whether it is a material breach of contract.

What rights do you have for defects of the flat?
SituationPeriod / rightLaw
Obvious defect at handoverreport without undue delaySection 2112: if you do not report a defect without undue delay after you could have discovered it on a timely inspection, the court will not grant you the right if the seller objects.
Hidden defect of the buildingwithin 5 years of acquisitionSection 2129(2): a hidden defect of a building attached to the ground by a solid foundation can be reported within five years of acquisition.
Defect appearing within 2 years (consumer)presumption that the flat was defective at handoverSection 2129(3): if a defect appears within two years of the passing of the risk of damage, the property is presumed to have been defective already then.
Material breach of contractrepair, discount or withdrawalSection 2106: remedy of the defect, a reasonable discount on the price or withdrawal from the contract; state your choice when reporting the defect.
Non-material breach of contractrepair or discountSection 2107: remedy of the defect or a reasonable discount; if the seller does not remedy the defect in time, a discount or withdrawal.
“Two-year guarantee as for goods”does not apply to a flatSection 2158: the provisions on the sale of goods to consumers (including section 2165) apply only to tangible movable things.
Obvious defect at handoverreport without undue delay
Section 2112: if you do not report a defect without undue delay after you could have discovered it on a timely inspection, the court will not grant you the right if the seller objects.
Hidden defect of the buildingwithin 5 years of acquisition
Section 2129(2): a hidden defect of a building attached to the ground by a solid foundation can be reported within five years of acquisition.
Defect appearing within 2 years (consumer)presumption that the flat was defective at handover
Section 2129(3): if a defect appears within two years of the passing of the risk of damage, the property is presumed to have been defective already then.
Material breach of contractrepair, discount or withdrawal
Section 2106: remedy of the defect, a reasonable discount on the price or withdrawal from the contract; state your choice when reporting the defect.
Non-material breach of contractrepair or discount
Section 2107: remedy of the defect or a reasonable discount; if the seller does not remedy the defect in time, a discount or withdrawal.
“Two-year guarantee as for goods”does not apply to a flat
Section 2158: the provisions on the sale of goods to consumers (including section 2165) apply only to tangible movable things.

What is the PENB and when do you get it?

The energy performance certificate of the building (průkaz energetické náročnosti budovy, PENB) must be obtained by the builder when constructing a new building (Act No. 406/2000 Coll. section 7a(1)). On a sale the seller shows it to the prospective buyer before the contract is concluded and hands it over at the latest when the purchase contract is signed; the energy class must also be stated in advertisements (section 7a(2)).

The certificate is valid for 10 years from issue, or until a major alteration of the completed building or a change of the heating method (section 7a(4)). For a flat it is the certificate of the whole building; on a later sale the unit owner requests it from the owners’ association (section 7a(3)) and, if they do not receive it, may replace it with the energy bills for 3 years (section 7a(7)).

How is the floor area of a flat measured?

The floor area of a flat in a unit is the plan area of all rooms of the flat including the area of all vertical load-bearing and non-load-bearing structures inside the flat, such as walls, columns and chimneys; the area is bounded by the inner face of the structures enclosing the flat (Government Regulation No. 366/2013 Coll. section 3). The area under built-in wardrobes and the bath counts too; the result is rounded to one decimal place.

The flat is bounded by the inner surfaces of its perimeter walls (section 2). A balcony, loggia, terrace or cellar is not a room of the flat, so listings state them separately. The floor areas of flats are also in the owner’s declaration, by which the unit comes into existence on entry in the land register (Civil Code sections 1164 and 1166). For VAT the floor area has been calculated differently since 1 July 2025, under Decree No. 163/2025 Coll.

If the flat lacks the characteristics agreed in the contract, including the area and the finish, that is a defect (sections 2095 and 2099). In the future purchase agreement, therefore, look at how the area is defined and what deviation is still permitted.

What is on sale today

New-build flats on sale (available and reserved), data as of 25 Nov 2026.

flats on sale in Czechia
9,639
of them in Prague
6,728
CZK/m², median for Czechia
174,088
CZK/m², median for Prague
187,072
flats on sale in Czechia
9,639
of them in Prague
6,728
€/m², median for Czechia
7,126
€/m², median for Prague
7,657

FAQ

Whether you can refuse the handover is set by the contract. Write defects that do not prevent the handover into the protocol with a deadline for remedy; you do not lose your rights for defects under sections 2106 and 2107 of the Civil Code by doing so.

What next

Sources: Building Act, No. 283/2021 Coll. (sections 230, 235 and 236); Civil Code, Act No. 89/2012 Coll. (sections 1164, 1166, 1186 and 2095–2129); Energy Management Act, No. 406/2000 Coll. (section 7a); Government Regulation No. 366/2013 Coll. (sections 2 and 3); Decree No. 163/2025 Coll. (floor area for VAT); Land Register Act, No. 256/2013 Coll. (section 10).

The guides are for information only and do not replace legal, tax or financial advice. Always check the terms of a purchase in the contract and with your bank.