In short
- What you pay before a contract is concluded is a deposit under the Civil Code, unless the contract says otherwise (section 1807).
- The developer is a business and you are a consumer: terms that create a significant imbalance of rights to your detriment are unfair and are disregarded (sections 1813 and 1814).
- A future purchase agreement binds the parties to conclude the purchase contract when called on within the agreed period, otherwise within one year (section 1785).
- Money in notary escrow belongs to the depositor until it is released to the recipient; the notary releases it only once you prove that the conditions in the record have been met (Notarial Code sections 89 and 89a).
What is a reservation agreement and what do you get for the fee?
By a reservation agreement the developer undertakes to hold the flat for you for an agreed time and offer it to nobody else; in return you pay a reservation fee. The Civil Code does not regulate reservation agreements specifically, so the wording decides: until when the reservation runs, what is to happen in that time (usually the signing of the future purchase agreement) and what happens to the fee.
What one party gives the other before a contract is concluded counts as a deposit under section 1807 of the Civil Code. The fee is therefore usually credited against the purchase price; when it is forfeited and when it is refunded must be stated expressly in the agreement.
The developer is a business and a buyer of a flat for their own use is a consumer, so the rules on consumer contracts apply (section 1810 et seq.). A term that lets the developer keep the fee if you do not conclude the contract, but gives you no reasonable compensation if the developer does not, is always unfair under section 1814(c).
- Until when the reservation runs and who is responsible for the next contract being signed within that period.
- When the fee is refunded: find out whether it is refunded even if the bank does not approve your mortgage.
- Whether the fee is credited against the purchase price and where you pay it.
What must a future purchase agreement contain?
By a future purchase agreement at least one party undertakes to conclude, when called on within the agreed period, otherwise within one year, a future contract whose content is agreed at least in general terms (Civil Code section 1785). With a flat from a developer you usually sign it after the reservation and before construction is completed.
If the entitled party does not call on the other party to conclude the contract in time, the obligation to conclude the purchase contract lapses (section 1788(1)). Compare the period for the call with the completion date. If the obliged party refuses to conclude the purchase contract, the entitled party can ask a court to determine its content (section 1787).
The content of the purchase contract need only be agreed in general terms; in practice you want more. The price, payment schedule, completion date, fit-out standards and the floor plan with the floor area should be in the contract itself or its annexes, not only in the sales brochure.
- The price and exactly what it covers (flat, cellar, parking space, share of the land).
- The payment schedule: how much, when and where you pay, and whether the deposits go into escrow.
- The completion date, the consequences of delay and the period within which the purchase contract can be called for.
- Standards and the floor plan as an annex; the floor area under Government Regulation No. 366/2013 Coll.
- The conditions under which you can withdraw and under which the developer can.
Which terms are prohibited in a consumer contract?
Under section 1814(1) of the Civil Code these terms are always unfair and are disregarded.
| Term | Law | What it means |
|---|---|---|
| The developer keeps what you paid if you do not conclude the contract; you get nothing if the developer fails to perform | section 1814(c) | Forfeiture of the fee must have a counterpart: reasonable compensation for you if the developer does not conclude the contract. |
| The developer can withdraw without reason, you cannot | section 1814(d) | The right to withdraw without reason cannot belong to the business alone. |
| After ending the contract at its own will, the developer keeps the money for what it did not deliver | section 1814(e) | Deposits paid for performance not provided are refunded. |
| The developer can change the rights and obligations of the parties on its own | section 1814(g) | Unilateral changes of standards or dates without your consent. |
| A price increase without a right to withdraw | section 1814(h) | On a substantial price increase you must have the right to withdraw from the contract. |
| A disproportionate penalty for a breach of your obligation | section 1814(l) | A contractual penalty for the buyer must be proportionate; a court may reduce an excessive one (section 2051). |
- The developer keeps what you paid if you do not conclude the contract; you get nothing if the developer fails to performsection 1814(c)
- Forfeiture of the fee must have a counterpart: reasonable compensation for you if the developer does not conclude the contract.
- The developer can withdraw without reason, you cannotsection 1814(d)
- The right to withdraw without reason cannot belong to the business alone.
- After ending the contract at its own will, the developer keeps the money for what it did not deliversection 1814(e)
- Deposits paid for performance not provided are refunded.
- The developer can change the rights and obligations of the parties on its ownsection 1814(g)
- Unilateral changes of standards or dates without your consent.
- A price increase without a right to withdrawsection 1814(h)
- On a substantial price increase you must have the right to withdraw from the contract.
- A disproportionate penalty for a breach of your obligationsection 1814(l)
- A contractual penalty for the buyer must be proportionate; a court may reduce an excessive one (section 2051).
Other terms are also unfair if, contrary to the requirement of good faith, they create a significant imbalance of rights to the consumer’s detriment (section 1813). This does not apply to terms on the main subject matter and on the price, provided they are clear and intelligible.
Where do the deposits go and how does escrow work?
Deposits under the payment schedule go either directly to the developer or into escrow (úschova), from which they are released once the conditions in the contract are met. Whether, and which part of, the purchase price goes into escrow is set by the contract; ask about it before you sign the reservation.
Notary escrow: you pay the money into a special account marked “notářská úschova”, and the notary draws up a record of its receipt that sets the deadlines and conditions for releasing the money to the recipient and how their fulfilment is to be proved (Notarial Code sections 86 to 88). Only once fulfilment of the conditions is proved does the notary release the money to the recipient (section 89); until then it belongs to the depositor (section 89a). The notary’s fee is set by the notary tariff.
Lawyer’s escrow: a lawyer accepts money only under a written contract, keeps it in a special lawyer’s escrow account and may handle it only under the conditions agreed in the contract (Legal Profession Act sections 52g and 52i). From 1 January 2026 the Bar’s guarantee fund compensates people harmed by a lawyer’s crime involving escrow, up to CZK 5 million per escrow where it concerns the purchase price of a property used for housing (section 29a). Bank escrow is governed by the contract with the bank.
What applies to contractual penalties and withdrawal?
A creditor may claim a contractual penalty regardless of whether the breach caused them any loss (section 2048). Paying the penalty does not release the debtor from the obligation the penalty secures (section 2049), and the creditor then has no right to compensation for loss from the same breach (section 2050). A court may reduce an excessive penalty on the debtor’s application (section 2051).
In the contract, therefore, look at whether the penalties apply to both sides: a penalty for your late payment should be balanced by a penalty for the developer’s late completion. When you can withdraw from the contract must be agreed; the law itself gives you no right to withdraw if, for example, your mortgage is not approved.
If the circumstances the parties evidently relied on when concluding the future purchase agreement change so that the obliged party cannot reasonably be required to conclude the contract, the obligation to conclude the purchase contract lapses; the obliged party must give notice of this without undue delay, otherwise it compensates the loss (section 1788(2)).
How fast flats sell
New builds across Czechia, last 7 days, data as of 25 Nov 2026.
- new flats on the market
- 53
- flats sold
- 68
- price cuts
- 18
- price increases
- 6
- new flats on the market
- 53
- flats sold
- 68
- price cuts
- 18
- price increases
- 6
FAQ
Only if the reservation agreement says so. The law itself creates no such right; look in the agreement for an express term on refunding the fee if the loan is not approved, and ask about it before you sign.
Under section 1807 of the Civil Code, what one party gives the other before a contract is concluded is presumed to be a deposit. The agreement may provide otherwise, though, for example treating the fee as a charge for the reservation; read what you sign.
The obligation to conclude the purchase contract lasts for the agreed period for the call, otherwise one year (section 1785). If the entitled party does not make the call in time, the obligation lapses (section 1788(1)). For a flat under construction the period should match the completion date.
Only if the contract allows it. A term that lets a business raise the price without giving you the right to withdraw on a substantial increase is always unfair (section 1814(h)).
The entitled party can ask a court, or a person named in the contract, to determine the content of the purchase contract (section 1787(1)). In addition, the contractual penalty and compensation for loss apply as agreed.
The law does not require it; the contract decides. Escrow with a notary, lawyer or bank releases the money to the developer only once it proves the agreed conditions are met, for example the entry of your ownership in the land register.
What next
Sources: Civil Code, Act No. 89/2012 Coll. (sections 1785–1788, 1807, 1810–1814 and 2048–2051); Notarial Code, Act No. 358/1992 Coll. (sections 86–89a); Legal Profession Act, No. 85/1996 Coll. (sections 29a, 52g and 52i); Notary tariff, Decree No. 196/2001 Coll.; Government Regulation No. 366/2013 Coll. (floor area).
The guides are for information only and do not replace legal, tax or financial advice. Always check the terms of a purchase in the contract and with your bank.